5th wheel man cave

Roofs done

6/6/2015. Roof finished

interior

Cabinets started.

 

Trim and lights

4/10/2015: Trim on door side and all of the electrical rough in with one working circuit for tools and deck lights.

 

Deck

4/9/2015. Removable deck started. 3 electrical circuits done.

 

 

Upstairs window 1

4/8/2015

Upstairs windows 2_edited-1

4/8/2015

Upstairs windows 3

4/8/2015. Upstairs windows in. Doorway to upper level created. 4 circuit breaker box installed.

 

2015 04 05_1585_edited-1

4/5/2015: Looking from the loft to the monitor/TV wall.

2015 04 05_1586_edited-1

4/5/2015: Looking at window wall from loft.

2015 04 05_1587_edited-1

4/5/2015: Looking at loft from monitor wall.

2015 04 05_1588_edited-1

4/5/2015: Looking at window wall from monitor wall.

2015 04 05_1590_edited-1

4/5/2015: Looking at monitor wall from downstairs corner.

 

Painted man cave_edited-2

4/4/2015. Outside painted and temporary steps built.

 

 

Door's in

03/29/2015

 

Finished siding 2

3/29/15

finished siding 2_edited-2

3/29/15

Finished siding

3/29/2015

 

First Siding

3/25/2015: A short day today. More this weekend.

 

 

Man cave Second floor roof

3/21/2015

 

 

 

IMG_4229[1]

3/21/2015 Second level walls. William and his family came back to help. Fun Day!!!!!!

IMG_4230[1]

3/21/2015

IMG_4235[1]

3/21/2015

 

 

IMG_4222

3/18/2015 Roof framed and osb installed first floor.

 

IMG_4223

3/18/2015

IMG_4224

3/18/2015

 

 

4th wall

3/15/2015 4th downstairs wall done. Noticed that the middle section wasn’t right.

4th wall repair

3/15/2015 Repair of the middle section. Thank God for the guy or girl that invented a sawzall.

4th wall with kim

3/15/2-15. Me William and Proud mom. Kimberly my oldest daughter.

 

Man cave wall 1

3/14/2015 My grandson William’s first framing job.

Man Cave Walls

3/14/2015

Man Cave Walls 4

3/14/2015

 

Man Cave Insulation_edited-1

3/8/2015. 3 1/2 inch styrofoam insulation between the joists.

3/8/2015.  Man Cave Painted Floor

3/8/2015. Glued, screwed and painted.

 

 

 

 

 

5th wheel frame2

03/04/2015 Sub floor ready for insulation and to be bolted to frame.

Man Cave Floor

03/04/2015

Trailer on pad 2

02/25/2015

Trailer on pad 1

02/25/2015

 

RV Pad

Pad before compacting

5th wheel frame

Delivery day. Waiting for the RV pad.

 

 

 

5th wheel

Trailer in its previous life. I never saw it like this. The previous owner had done all the hard work for me.